BigSim
-
Is there a reg that states the main earth bonding cable (gas,water,etc), needs to go to the MET? I've checked the regs, apart from being continuous and within 600mm of the incoming supply, I couldn't find anything specific. I've been told (by somebody with a higher pay grade), that you can run it to a sub-board. If this was the case (something which I've never done, and thought it was frowned upon), I'm assuming the requirements for the min size of the cpc supplying said DB would also have to be adequate?