... for example 3 hours to relocate the cooker switch seems a bit much
2.50 hours for cooker switch agreed by you .not .for example 3 hours to relocate the cooker switch seems a bit much
Not really depends on how far and what the routing was like.... for example 3 hours to relocate the cooker switch seems a bit much
once the test cert are handed over then is down to the customer use the ones to do the remedial work or get some body in just to test.I would in future get the EICR done by a firm that maybe only did testing.
You should have asked to have the test done, cert issued followed by a quote for remedial repairs, this should have been agreed prior to ANY testing taking place, unless of course you gave Matey Carte Blanche to repair as he went along with the EICR, in my opinion.I think the labour cost is about 21 hours. There's another £288 which is the cost of the EICR and PAT testing, which is fine, we knew that was a fixed cost. There's nearly £300 for materials as well, which we naturally accept. Altogether though it feels like a lot - but I wanted to come here and find out your thoughts before I did anything about it.
I totally agree (now, with the benefit of hindsight) Taylortwocities, I would in future get the EICR done by a firm that maybe only did testing.