Hello. Its my first time here and i am after some advice. my grandmother has had an electrical report done by an NICEIC electrician. He found quite a few things wrong with the property and has been pressuring my nan to get the work done asap!! which i dont think is right. I think he has rang about 4 times in 2 days.
The property is 40 years old and i understand that some things are probably not up to regs but wanted to double check as i have had some experience in the electrical field whilst in the forces but by no means an expert.
His report says,
bonding to gas undersized (6mm)
water bond undersized (6mm)
bonding conductor undersized (6mm) t n c s supply???
There is an older style wylex fusebox with 6 circuit breakers. He has said that we need to get that changed because the property has no rcd trip switch.
2 way lighting cable has no cpc. rewire?
there are also 2 more small fuseboxes next to the wylex. these both have rcd trip switch. 1 for shower and 1 for extra sockets. these 2 fuseboxes get there supplies from the original wylex. he says the supply cables going to the 2 fuseboxes are sized wrong. What size do they need to be? the shower fusebox turns off by a 32amp circuit breaker and the extra socket one turns off by a 32amp circuit breaker.
Apologies for the long message but wanted to give out as much info as possible.
Any help would be greatly recieved.
Dan.
 
What has he coded C1? C2 and C3?

Thats what is important - or could you upload a copy of the report (remove his details)

As for calling 4 times in 2 days - I'd simply ask him to provide an estimate for each item so you can understand the costs.

I'd say none of these are urgent.

Hope this helps.
 
So are you asking for his findings to be contradicted or to condemn him for pestering her for him to do the work?
 
the report has numbers 1,2,3,4 the report looks like a print off from a template. i looked on the nic website and his report looks nothing like the one i have. i have checked him out though and he is registered
he has put them all as 2
what i dont understand is should this work be done just on the say so of an electrician? i am of the attitude of 'if it aint broke'
 
yeah, the pestering i find a bit ott. just want a bit of advice. by the way he has estimated a cost of £725 to do all the work.
 
the report has numbers 1,2,3,4 the report looks like a print off from a template. i looked on the nic website and his report looks nothing like the one i have. i have checked him out though and he is registered
he has put them all as 2
what i dont understand is should this work be done just on the say so of an electrician? i am of the attitude of 'if it aint broke'
Ask someone else for a second opinion, sure you will find someone on this forum in your area. Quotes are free.
 
Upload a copy?? apologies, my son would have to do that and he is away. i can give you more info from the cert if it helps.
What has he coded C1? C2 and C3?

Thats what is important - or could you upload a copy of the report (remove his details)

As for calling 4 times in 2 days - I'd simply ask him to provide an estimate for each item so you can understand the costs.

I'd say none of these are urgent.

Hope this helps.
 
from what you say, it looks like the "faults" he has listed are commom to thousands of other installations of similar age. ask him to give you an itemised quote for the work he says you need doing and you will consider it. meanwhikle, get a second and maybe a third qoute. there are forum members close to you, imago, for one, who, i'm sure, would be happy to give a quote.
 
OK many thanks. i alreadt have another electrician here in the morning but am happy to get another opinion. i would like a clearer idea or get the work done if needed as i am due back in germany start of feb and dont wont nan to deal with it.
Thankyou again for your time and help.
from what you say, it looks like the "faults" he has listed are commom to thousands of other installations of similar age. ask him to give you an itemised quote for the work he says you need doing and you will consider it. meanwhikle, get a second and maybe a third qoute. there are forum members close to you, imago, for one, who, i'm sure, would be happy to give a quote.
 
If he pesters your Gran again, tell him you'll punch him on the nose, or report him to the police.
Yes 6mm² is undersized for the current thinking and Regulations.
However unless there are indications of overheating, the current thinking is there is no requirement to upgrade to 10mm².
It may be that the cables used to supply the two small CUs are undersized, but then again not.
If those cables are less than 3m in length, then very likely they are fine.
There are now requirements for some cables, some socket-outlets and some circuits to be provided with 30mA RCD protection.
However an installation that does not have such protection is not necessarily unsafe, and there is no requirement to upgrade such an installation.
To be honest, the 32A MCB does appear to be too haigh a rating for a single socket-outlet, 20A or 16A would be to my mind more appropriate.
Changing such should not really cost any more than £20 - £30.
 
the report has numbers 1,2,3,4 the report looks like a print off from a template. i looked on the nic website and his report looks nothing like the one i have. i have checked him out though and he is registered
he has put them all as 2
what i dont understand is should this work be done just on the say so of an electrician? i am of the attitude of 'if it aint broke'

Interesting. code 4's stopped being used at the end of 2011
 
has he filled in a periodic instead of a eicr?
only the socket sounds dodgy although it would be nice for a copy so we can see in detail.
 