J
jmc1683
so I'm 2nd fixing a large house in north london, weeks ago I ran a 10mm 4 core (3 phase) cable to the steam room and the sauna in opposite sides of house, each going to a 3 phase isolator, at the time I didn't know the load requirements and so I chose 4 core as precaution, I only need single phase at each of these locations, my question is do you think I should still install 3 phase MCB in board on each of these cables or fold back the un neeeded phases at the board as another electrician has suggested to me? may sound like stupid question but I've never been in this position before, I don't see a problem in conecting them in 3 phase MCB's as they are properly connected in 3 phase isolators at other end. what to do you think?