A customer has asked me to quote for some work and he sent a copy of the EICR that was done a while back. As can be seen, the person who did the eicr is holding back the test results until the C2's have been resolved?
I don't do many EICRs mainly because there are locals doing them too cheap and I'm not prepared to sink to their level, but regardless of whether there are C2s, if I'm being paid to do an EICR then the customers get the full test results regardless of what issues I've found.
Am I missing something?
I don't do many EICRs mainly because there are locals doing them too cheap and I'm not prepared to sink to their level, but regardless of whether there are C2s, if I'm being paid to do an EICR then the customers get the full test results regardless of what issues I've found.
Am I missing something?