The consumer units are in outdoor buildings, each running minimal lights & 2 plug sockets. The cables are all in place, it's literally just replacing four old consumer units with new ones. Tia!
 
would need to look at them first tbh, if the protective bonding doesn't need replacing id say 2 very full days to do the change and test each board.
hit faults with testing or have to run new protective bonding a board a day.
 
It sounds like each board is just 2 circuits - lights, sockets - with 1 or 2 lights and 2 sockets total. If so, and everything complies and tests good, could probably manage all 4 in a full day, per James's post. This assumes my choice of board, and not something cheap and nasty that I'm not familiar with. But could easily take a lot longer, and I'd not give any firm costs without having seen them.
 

OFFICIAL SPONSORS

Electrical Goods - Electrical Tools - Brand Names Electrician Courses Green Electrical Goods PCB Way Green 2 Go Pushfit Wire Connectors Electric Underfloor Heating Electrician Courses Heating 2 Go
These Official Forum Sponsors May Provide Discounts to Regular Forum Members - If you would like to sponsor us then CLICK HERE and post a thread with who you are, and we'll send you some stats etc

Advert

Daily, weekly or monthly email

Thread starter

Joined
Location
Cheshire
If you're a qualified, trainee, or retired electrician - Which country is it that your work will be / is / was aimed at?
United Kingdom
What type of forum member are you?
DIY or Homeowner (Perhaps seeking pro advice, or an electrician)

Thread Information

Title
Hi! Could any electricians estimate how long it would take to replace 4 consumer units.
Prefix
N/A
Forum
UK Electrical Forum
Start date
Last reply date
Replies
8
Unsolved
--

Advert

Thread statistics

Created
Jo Harvey,
Last reply from
Dustydazzler,
Replies
8
Views
1,221

Advert

Back
Top