Please if anybody can help where in the BS7671 does it state who is responsible for ME bonding on a new Instalation (barn convertion to ho;iday flats)
 
The person designing the installation is responsible for designing it.

The person installing it is responsible for installing it.

The person inspecting and testing it is responsible for inspecting and testing it.
 
Did you leave it for the plumbers to connect up?

Seen a few houses now that had a 10mm2 earth wire run all the way from the MET to under the sink, but never actually attached to the pipe as presumably it had been left for the plumbers to sort out or something.

Not sure how they managed to pass them on the inspection and testing.... probably got the plasterers to do that or something.
 

OFFICIAL SPONSORS

Electrical Goods - Electrical Tools - Brand Names Electrician Courses Green Electrical Goods PCB Way Green 2 Go Pushfit Wire Connectors Electric Underfloor Heating Electrician Courses Heating 2 Go
These Official Forum Sponsors May Provide Discounts to Regular Forum Members - If you would like to sponsor us then CLICK HERE and post a thread with who you are, and we'll send you some stats etc

Advert

Daily, weekly or monthly email

Thread Information

Title
Main Equipotential bonding
Prefix
Forum
UK Electrical Forum
Start date
Last reply date
Replies
19
Unsolved
--

Advert

Thread statistics

Created
Spider-me,
Last reply from
bf03yvd,
Replies
19
Views
2,091

Advert

Back
Top