Thanks. They ask for 2 new circuits. Just need to find something suitable.What does Napit exactly ask for, should be your first question. You could go do some work in a family members property, if your own Consumer Unit doesn't require replacement.
I like this idea. Would you do the sockets as a ring circuit?Garage Makeover Project is be my suggestion.
Distribution circuit in SWA, CU refresh and 2 new socket circuits.
If you do an RFC you might only need one new circuit ...Would you do the sockets as a ring circuit?

Good idea , thanks. Think I will go along these lines and do it in pvc conduit.If you do an RFC you might only need one new circuit ...![]()
You, as the designer of the new installation, are the person who makes this decision based on the customer's reqirements.I like this idea. Would you do the sockets as a ring circuit?
Perhaps I’m being harsh, but I think Inspector Gadget would just love to pick up on this and give a ‘non conformance’ to remedy.Use steel saddles for the pvc conduit to prevent premature collapse in the event of a fire.
IMO, if you do a DB change you have theoretically changed the method of protection for all the circuits, therefore will now require retesting to complete a EIC...If you do a consumer Unit change, do you still need to install another circuit to meet 2 circuit requirements for Napit assessment or CU change itself is enough to meet the requirement?