On 'Pattesters' website they advise-

When testing modern IT equipment it is not normal to performed a leakage or touch current test; these tests are usually used on older equipment in place of the 500 Volt insulation test.

However in my copy of the IEE they say that touch current test should be used.

So if you are not using a leakage or touch current, I presume the only tests they are saying used on it are visual inspection & earth continuity test.
 
Correct!! The reason being; modern PC's momentarely start up when you apply power, then shut down automatically after about 10 seconds. When PAT testing the applied test duration is around 5 seconds. When 2 short bursts of power is applied to modern PC's
there is a potential of them "crashing".
 

OFFICIAL SPONSORS

Electrical Goods - Electrical Tools - Brand Names Electrician Courses Green Electrical Goods PCB Way Green 2 Go Pushfit Wire Connectors Electric Underfloor Heating Electrician Courses Heating 2 Go
These Official Forum Sponsors May Provide Discounts to Regular Forum Members - If you would like to sponsor us then CLICK HERE and post a thread with who you are, and we'll send you some stats etc

Advert

Daily, weekly or monthly email

Thread Information

Title
P.A.T Testing I.T. Equipment
Prefix
N/A
Forum
Electrical Testing & PAT Testing Forum
Start date
Last reply date
Replies
2

Advert

Thread statistics

Created
PAT ukLtd,
Last reply from
PAT ukLtd,
Replies
2
Views
2,356

Advert

Back
Top