in order to facilitate the relocation of an electrical meter from the ground to 1st floor UKPN has asked me to install a what they are calling a read head cut out within the 1st floor by the consumer fuse board to facilitate their new electrical meter position which will be installed by another party.

What is a red head cut out and why does it need to be there?
 
I have only ever heard or redlink which is a solid fuse link placed in the Henley block when the main cutout fuse is in a different location
 
They look a bit like this, there's a solid link in the fuseholder which looks like a bit if steel pipe.
You occasionally get people (Electrical Trainee's and the like) who don't know what they are doing posting pictures saying that the DNO has bypassed the fuse and caused a dangerous situation when it is intended to be an isolation link.

hcs71pner-image.jpg
 
They look a bit like this, there's a solid link in the fuseholder which looks like a bit if steel pipe.
You occasionally get people (Electrical Trainee's and the like) who don't know what they are doing posting pictures saying that the DNO has bypassed the fuse and caused a dangerous situation when it is intended to be an isolation link.

View attachment 48645
I saw one of those today. There is no fuse in it, just a piece of metal which is dangerous so I have reported it to the DNO.
 

Reply to Relocation of electrical meter in the UK Electrical Forum area at ElectriciansForums.net

Similar Threads

Hi there, I built a house with ground source heating 5 years ago and it's a fairly large house so I have 3 phase supply 80 amps per phase. I had...
Replies
7
Views
897
Good morning all, I am currently working on a House in Multiple Occupation (HMO) consisting of 10 flats, with three parking spots equipped with...
Replies
9
Views
506
Hi all, Very much a novice when it comes to electrics. Anyway, we're getting an EV chargepoint installed, but before we do, I was wondering what...
Replies
3
Views
498
I am planning to go semi off grid with a victron and battery system. The system will be installed in an out building about 20 meters away from...
Replies
7
Views
680
Evening Gents just after a bit of advice and what would you do differently. I have wired up 3 kw heaters in 4mm tuff cable (40 meter distance...
Replies
2
Views
242

OFFICIAL SPONSORS

Electrical Goods - Electrical Tools - Brand Names Electrician Courses Green Electrical Goods PCB Way Electrical Goods - Electrical Tools - Brand Names Pushfit Wire Connectors Electric Underfloor Heating Electrician Courses
These Official Forum Sponsors May Provide Discounts to Regular Forum Members - If you would like to sponsor us then CLICK HERE and post a thread with who you are, and we'll send you some stats etc

Electrical Forum

Welcome to the Electrical Forum at ElectriciansForums.net. The friendliest electrical forum online. General electrical questions and answers can be found in the electrical forum.
This website was designed, optimised and is hosted by Untold Media. Operating under the name Untold Media since 2001.
Back
Top
AdBlock Detected

We get it, advertisements are annoying!

Sure, ad-blocking software does a great job at blocking ads, but it also blocks useful features of our website. For the best site experience please disable your AdBlocker.

I've Disabled AdBlock