I'm interested to know how its being hooked up because I would of thought it would only need the PV circuit isolating and not the whole building.


The he board serves the entire building, all in one three phase board for all 4 units, with no sub boards, it's a poor layout. Anyway, it needs two new circuits putting in.

I'll tell him not a chance, he will have to switch it off.
 
Jesus Christ Mike!! That's just going to encourage him!!

As a matter of interest... What did it feel like? Tingle? massive shock? Somewhere in between?
I have had some bad belts in my time steve, the worse believe it or not was at a school in Stroud, your neck of the woods, I disconnected 2 neutrals in a switch when I was just out of my time when the switch was on and I ended up making the circuit, it was switching 8 6ft fluorescent lights, I had a terminal screwdriver in my hand at the time and the shock made me flinch quite violently, the screwdriver ended up stuck in the door the other side of the room, the senior spark on the job gave me a good --- kicking, I learnt my lesson regarding neutrals and fluorescents.
 
I had a bit of a zap in my very own home, I'd been doing the bathroom and moving walls around, put a new drop down for a light switch in back room, connected looft light up etc, and forgot I'd left a drop for a switched it back on, went back upstairs, switched landing light on, yep ok, check loft light, yep ok, went it back room and caught the back of my hand on cut wire, I felt it but not enough to trip the RCD.
 
Jesus Christ Mike!! That's just going to encourage him!!

As a matter of interest... What did it feel like? Tingle? massive shock? Somewhere in between?
Over at pagan hill in stroud there used to be a factory called the pattern centre, I believe you have a co-op there now, it is quite close to the fire station near whites hill, I was about 17 and the guy who was training me was working on some old heavy switch gear, the very old orange painted type, the boards were 15 ft up in the air in the main factory. We had a tower up to them, he asked me where I thought the live parts in the board were, Like a fool I touched the busbar and said here to him at the same time here,I fell to the floor due to the shock, funnily enough it never hurt that time lol, he then asked me what the hell I thought I was doing, I said you said where are the live parts, he said I asked you to tell me not show me haha, I was just a kid really and never did that again.
 
nothing wrong with live working usually but you need to make a judgement call.

the only time ive been part of a shutdown was because the isolators we needed to connect the supply into were on the top of a busbar chamber and after removing the cover to have a look at the isolator there is nothing to stop screws or swarf etc falling below onto the bars.

why not ask them about planning a shutdown? we do this from time to time because of the nature of the work we do.

we do the controls, fans etc for isolation wards in hospitals etc some of them we are not allowed to go in without a very good reason without a shutdown.
 
A visual inspection followed by a RA would be my preference. then if the risk factor was acceptably small, then i'd do it live.
 
You have said that you are not happy with working live, this really gives you the answer you need.
If you are not confident in doing a job then this is when things will go wrong.
You have the support of the law to back you up in your choice and you have the support of common sense to reinforce this.

I realise that customers value your life at less than their television (or radio in this case) programs but I hope you may value your own life slightly more.

Unless you agree with the customer it will cost an additional £4000 for you go on a live working training course and purchase the additional PPE and tools required.
 
A visual inspection followed by a RA would be my preference. then if the risk factor was acceptably small, then i'd do it live.

What good would it possibly do to know the resistance Tel? :D
 
If you haven't looked at the switchgear/dis boards yet then how do you know you need to shut down the whole building?
 