I am doing a rewire in a Victorian house with split floor levels:
Basement
Lower Ground Floor
Upper Ground Floor
Lower First Floor
Upper First Floor
Second Floor
I have a limited amount of space to install the CU and cant fit anything bigger than a 16 module board (so have opted for a main switch and up to 14 ways for RCBOs arrangement). The Basement is being rewired by another contractor (as it is being completely renovated and the builder brought his own spark) and he needs three ways, which leaves me with 11. It is possible to provide separate power and lighting circuits for every sub-floor but it would leave the CU with no spare ways for future additions e.g.
Lower Ground Floor - 3 circuits (oven, ring final, lights)
Upper Ground Floor - 2 circuits (sockets, lights)
Lower First Floor - 2 circuits (sockets, lights)
Upper First Floor - 2 circuits (sockets, lights)
Second Floor - 2 circuits (sockets, lights)
Can any of you see any reason regs wise (I've calculated demand and its fine) why I couldn't merge some of these so the circuits are as follows:
circuit 1: oven
circuit 2: ring final lower ground floor
circuit 3: sockets upper ground and upper first floor
circuit 4: sockets lower first and second floor
circuit 5: lights lower ground and lower first floor
circuit 6: lights upper ground floor
circuit 7: lights upper first floor
circuit 8: lights upper second floor
I can't see a problem with it regarding division of circuits but as I've not done it this way before thought I'd open it up to you lot for some (hopefully) constructive criticism.
Thanks
Basement
Lower Ground Floor
Upper Ground Floor
Lower First Floor
Upper First Floor
Second Floor
I have a limited amount of space to install the CU and cant fit anything bigger than a 16 module board (so have opted for a main switch and up to 14 ways for RCBOs arrangement). The Basement is being rewired by another contractor (as it is being completely renovated and the builder brought his own spark) and he needs three ways, which leaves me with 11. It is possible to provide separate power and lighting circuits for every sub-floor but it would leave the CU with no spare ways for future additions e.g.
Lower Ground Floor - 3 circuits (oven, ring final, lights)
Upper Ground Floor - 2 circuits (sockets, lights)
Lower First Floor - 2 circuits (sockets, lights)
Upper First Floor - 2 circuits (sockets, lights)
Second Floor - 2 circuits (sockets, lights)
Can any of you see any reason regs wise (I've calculated demand and its fine) why I couldn't merge some of these so the circuits are as follows:
circuit 1: oven
circuit 2: ring final lower ground floor
circuit 3: sockets upper ground and upper first floor
circuit 4: sockets lower first and second floor
circuit 5: lights lower ground and lower first floor
circuit 6: lights upper ground floor
circuit 7: lights upper first floor
circuit 8: lights upper second floor
I can't see a problem with it regarding division of circuits but as I've not done it this way before thought I'd open it up to you lot for some (hopefully) constructive criticism.
Thanks