Ossy
Does anyone know if the reset delay on the Solarmax 13MT can be adjusted and if so how?
We have a site with 9 x inverters and it would be good if we could adjust the reset delay on each inverter to achieve a staggers start over a period of time following a power outage and prevent a possible shock load to the grid and G59/2 relay which could cause an overvoltage to occur and thus trip the G59/2 relay. Obviously this would only occur when a peak output and shutdown coincide, but it is still a possibility.
We have a site with 9 x inverters and it would be good if we could adjust the reset delay on each inverter to achieve a staggers start over a period of time following a power outage and prevent a possible shock load to the grid and G59/2 relay which could cause an overvoltage to occur and thus trip the G59/2 relay. Obviously this would only occur when a peak output and shutdown coincide, but it is still a possibility.