each one on it's own circuit, maybe separate board. couple of ways to have them on 12 midnight to 7am. timeswitching and/or dual tariff meter.
 
More info needed.

Are these heaters replacements for existing Storage heaters?

They can't be connecting Off peak storage heaters to an always On Ring circuit, the heaters will be on all the time.
Are they just connecting the control circuit for the heater to the Ring and using an existing Off peak supply for the heating load?

Are they altering the existing circuit wiring, or are they only connecting the heaters to existing FCU / Double pole switches.?
 
More info needed.

Are these heaters replacements for existing Storage heaters?

They can't be connecting Off peak storage heaters to an always On Ring circuit, the heaters will be on all the time.
Are they just connecting the control circuit for the heater to the Ring and using an existing Off peak supply for the heating load?

Are they altering the existing circuit wiring, or are they only connecting the heaters to existing FCU / Double pole switches.?I its the control there connecting to the ring and then using a existing off peak supply for the heating, and connecting to FCUs , not altering circuit wiring unless heater has to go in another location, but there not installing rods when there isn't one.
 
More info needed.

Are these heaters replacements for existing Storage heaters?

They can't be connecting Off peak storage heaters to an always On Ring circuit, the heaters will be on all the time.
Are they just connecting the control circuit for the heater to the Ring and using an existing Off peak supply for the heating load?

Are they altering the existing circuit wiring, or are they only connecting the heaters to existing FCU / Double pole switches.?
More info needed.

Are these heaters replacements for existing Storage heaters?

They can't be connecting Off peak storage heaters to an always On Ring circuit, the heaters will be on all the time.
Are they just connecting the control circuit for the heater to the Ring and using an existing Off peak supply for the heating load?

Are they altering the existing circuit wiring, or are they only connecting the heaters to existing FCU / Double pole switches.?
There connecting the control to the ring and the heater to the off peak supply and connecting to a existing FCU , sometimes the circuit is altered if the heater has to go in another location . But there not installing an RCD in situations where the is no RCD protection in the house . Sometimes they do connect the heater direct to the ring when there is no off peak supply.
 
The new 'smart' storage heaters can be connected to a single 24 hour supply with the two sets of terminals within linked then programmed so that the main 'core' only draws power during the off peak period - assuming there is an existing dual tariff supply in place.
 
The new 'smart' storage heaters can be connected to a single 24 hour supply with the two sets of terminals within linked then programmed so that the main 'core' only draws power during the off peak period - assuming there is an existing dual tariff supply in place.
I was installing storage heaters for over a year and used both the Elnur Gabbaron and Dimplex quantum. The Elnur are more high maintenance with settings each heater had its own dedicated supply off peak and the on peak we would use fused spur although need to be careful as the large ones have a balance element which is powered via the on peak supply and should the heater require topping up for heat the element would kick in so if you have a number of heaters and one ring main could overload circuit. Took me a while to master the controls of the Elnur gabbarons but once fully understood they are good heaters
 
I was installing storage heaters for over a year and used both the Elnur Gabbaron and Dimplex quantum. The Elnur are more high maintenance with settings each heater had its own dedicated supply off peak and the on peak we would use fused spur although need to be careful as the large ones have a balance element which is powered via the on peak supply and should the heater require topping up for heat the element would kick in so if you have a number of heaters and one ring main could overload circuit. Took me a while to master the controls of the Elnur gabbarons but once fully understood they are good heaters
Another factor is not every household is off peak midnight till 7am and this causes problems with the heaters you need to alter the settings which isn’t straight forward you will have an error 4 message every morning if the heaters are out of sync with timing for off peak
 

OFFICIAL SPONSORS

Electrical Goods - Electrical Tools - Brand Names Electrician Courses Green Electrical Goods PCB Way Green 2 Go Pushfit Wire Connectors Electric Underfloor Heating Electrician Courses Heating 2 Go
These Official Forum Sponsors May Provide Discounts to Regular Forum Members - If you would like to sponsor us then CLICK HERE and post a thread with who you are, and we'll send you some stats etc

Advert

Daily, weekly or monthly email

Thread starter

Joined
Location
Manchester
If you're a qualified, trainee, or retired electrician - Which country is it that your work will be / is / was aimed at?
United Kingdom
What type of forum member are you?
Practising Electrician (Qualified - Domestic or Commercial etc)

Thread Information

Title
storage heaters
Prefix
UK 
Forum
UK Electrical Forum
Start date
Last reply date
Replies
11
Unsolved
--

Advert

Thread statistics

Created
L1Jay1,
Last reply from
Dave OCD,
Replies
11
Views
3,658

Advert

Back
Top