Sintra

Ok i have to price for PIR's on numerous properties but the only information i have is the floor area of each property.

Now i remember a thread similar to this coming up before and my advise was to visit the property and try and determine how many DB's, circuits etc. were involved and calculate from that at a per circuit rate.

My problem is these properties are all over North America and i just don't have time to visit them (much as i would like to).
Normally we get a lot more information from the client to price from like amount of DB's and ways in each.

Any help on this would be much appreciated.
 
Unfortunatley i can't find out the number of circuits involved only the floor area of each property that's were i'm screwed.
 
Oh, here we go again, damn beginners! Barely makes a post and wants his business run for him...... :D :D :D

The best help we can give on this forum is to take two aspirin, and have a long lie down in a darkened room.

Alternatively, my spread sheet has just calculated that from Belfast, you can make a small profit, providing you charge a reasonably generous £1825.75 a circuit. This allows 30 minutes a circuit, travel time, and inter-state injections.

Then there's the number of remedials you'll find - given that no American I've ever come across has the first clue about safe electrical practice, and I can safely bet that not one of the jobs you'll visit comes anywhere near BS7671.

To be honest, I think testing in the States is fairly easy.

Lick finger, stick in socket, award points for the dance.

Hope this helps.

Happy New Year, Sintra :D
 
Blimey mate, that's a toughie.

It would be hard enough to do in the UK let alone NA, cant really see how TBH.

Are you perhaps able to source some kind of plans/drawings of other houses in NA of similar size to the floorplan of yours and see if there is an electrical schematic you could base your costing on???
 
Ok i have to price for PIR's on numerous properties but the only information i have is the floor area of each property.

Now i remember a thread similar to this coming up before and my advise was to visit the property and try and determine how many DB's, circuits etc. were involved and calculate from that at a per circuit rate.

My problem is these properties are all over North America and i just don't have time to visit them (much as i would like to).
Normally we get a lot more information from the client to price from like amount of DB's and ways in each.

Any help on this would be much appreciated.

Um.....

Having posted........you're not serious?

Best bet, if it is a real one........use local contractors - get their prices and add a mark up, stay warm at home.
 
Cheers Bill and a happy new year to you also.

Unfortunately it's not quite as easy as that. The properties are all British Govt owned and wired to bs7671 so unfortunately they have to be tested to our standards.
Think getting a price in for this one will be a bit of guess work trying to work out times per 100 Sq M of floor space.

Sorry also for asking for advice before reaching 10,000 posts.;)
 
Blimey mate, that's a toughie.

It would be hard enough to do in the UK let alone NA, cant really see how TBH.

Are you perhaps able to source some kind of plans/drawings of other houses in NA of similar size to the floorplan of yours and see if there is an electrical schematic you could base your costing on???

Most of it is offices although there are a number of residences involved. I do have a list of addresses so might have a look on google earth first of all to see what i'm up against.
 
Um.....

Having posted........you're not serious?

Best bet, if it is a real one........use local contractors - get their prices and add a mark up, stay warm at home.

I am serious on this one Bill. Not able to use local contractors unfortunately.
 
You could try searching for an ex pat electrical QS or such like in the states to relay the info back to you or subcontract the estimation, Or pay a local contractor to tot up circuits and boards
 
Cheers Bill and a happy new year to you also.

Unfortunately it's not quite as easy as that. The properties are all British Govt owned and wired to bs7671 so unfortunately they have to be tested to our standards.
Think getting a price in for this one will be a bit of guess work trying to work out times per 100 Sq M of floor space.

Sorry also for asking for advice before reaching 10,000 posts.;)

Oops! Sorry my friend......I genuinely thought it was a wind up.

Given you're a mod, I guess you're allowed to ask advice after only 3000 posts lol :D

To be honest, I'd go on a rate per Sq m, then, given that we know roughly how big a ring final is allowed to be.

Do you have to break the price down into test/remedial/travel/misc?

Or has your price got to include everything?

How many buildings - may be worth taking a "minor" punt on a price per building if you also get some "holiday" time in it.?
 
You could try searching for an ex pat electrical QS or such like in the states to relay the info back to you or subcontract the estimation, Or pay a local contractor to tot up circuits and boards

Very good idea but in this instance it would not be possible.
 
Oops! Sorry my friend......I genuinely thought it was a wind up.

Given you're a mod, I guess you're allowed to ask advice after only 3000 posts lol :D

To be honest, I'd go on a rate per Sq m, then, given that we know roughly how big a ring final is allowed to be.

Do you have to break the price down into test/remedial/travel/misc?

Or has your price got to include everything?

How many buildings - may be worth taking a "minor" punt on a price per building if you also get some "holiday" time in it.?

Price has to be broken down into location basically.

So for each city irrelevant of the number of properties i need to submit a price.

Then i need to allow for all flights which will be a hell of a lot.

Accomodation & transport in all cities except Washington & New York were it is all provided.
 