What should you do when you fill out a EIC for just a CU change and the existing circuits are not to regs or have little bits like the switch live not sleeved etc?
What should you do when you fill out a EIC for just a CU change and the existing circuits are not to regs or have little bits like the switch live not sleeved etc?
Yep, so long as they would only be classed as a Code 4 if you were doing a PIR you'll be fine. Any code 1 or 2s and you shouldn't be changing the consumer unit until those sorts of faults are repaired or disconnected.