Global IR testing on 3phase

Discuss Global IR testing on 3phase in the UK Electrical Forum area at ElectriciansForums.net

It's no different to single-phase. For commissioning (and EICR if you can be sure all loads are disconnected) test each wire to each other wire. For EICR with loads still assumed to be connected, three lines and neutral paralleled to earth.
 
It's a very good point. When I open a neutral link for testing, especially if it is going to be left open for a while, I put a reminder on the isolator lockout so that it does not get overlooked when re-energising. I have never powered a system back up with the neutral open, but having spent many hours repairing the aftermath of neutral loss events, I don't want to cause one myself.
 

Reply to Global IR testing on 3phase in the UK Electrical Forum area at ElectriciansForums.net

OFFICIAL SPONSORS

Electrical Goods - Electrical Tools - Brand Names Electrician Courses Green Electrical Goods PCB Way Electrical Goods - Electrical Tools - Brand Names Pushfit Wire Connectors Electric Underfloor Heating Electrician Courses
These Official Forum Sponsors May Provide Discounts to Regular Forum Members - If you would like to sponsor us then CLICK HERE and post a thread with who you are, and we'll send you some stats etc
This website was designed, optimised and is hosted by untold.media Operating under the name Untold Media since 2001.
Back
Top