There is some mention of hospitals in BS7671 in timing of generators switchover and earthing systems peculiar to hospitals.
Section #?
There is some mention of hospitals in BS7671 in timing of generators switchover and earthing systems peculiar to hospitals.

but what do they mean by "risk grade"?
It's not law that would cover it, it would be Health Service Policy.And one question- I can legally supply backup power for the whole site via one ATS?
The level of Risk of an electrical supply failure causing harm to Patients and or the Business.
Example,
Loss of power to Car park lighing .
Risk Grade 4. Consequences, low risk of trips and slips.
Loss of power to Operating theatre.
Risk Grade 1. Consequences, high risk of loss of Patient life.
So what would mandate multiple ATSs?
Anyone have a single line of an actual UK hospital?
I doubt actual line diagrams of an in service hospital would be available online. However there may be theoretical ones.
It's a bit of a niche subject.
Can you define what you mean by ATS. I presume alternate supply?
Nothing government funded? What, the NHS is gov right? Then they should have single lines out there.
ATS= Automatic Transfer Switch