It would very much depend on a number of things....
Who's supplying materials?
How complex is the containment?
How quick are you going to be - e.g. how adept are you with galv conduit?
Who's covering the cost of consumables like drill bits and fixings etc.
Normally, for any point price, we'd expect the point price to include: Cable, fixings, containment, installation of terminated device, termination at DB or panel. We would supply terminated device - e.g. spur, light fitting, whatever.
So, if you're doing it by point, those are things you've got to consider, so your point price will reflect that. It may be better for you not to work on a point price, and instead offer a price for the job. Work out what you're supplying, and you time and charge accordingly.