O
Octopus
Pre RCD (General RCD covering whole installation - all CUs)
ah ha, and upfront RCD. Nice.
Pre RCD (General RCD covering whole installation - all CUs)
Do you know how a RCD actually works?
it monitors for a imbalance in current between the two live conductors, it has nothing to do with the earthing arrangement of the property.
Well find the information you are referring too, then have a look and see if it will affect the RCD in this instance. Personally I would say there is still a load connected somewhere that is causing the problem.
My recommendations:
Install new Earth Electrode!!!!
Install Gas Bonding
Install new CU
Cant recommend anything with regards to circuit 6 at present as could not identify any particular fault
what sort of nic os the service head in?My recommendations:
Install new Earth Electrode!!!!
Install Gas Bonding
Install new CU
Cant recommend anything with regards to circuit 6 at present as could not identify any particular fault
Far too sensible as usual Biff ;-)