Pricing for a full junior school eicr
I know its difficult without visiting site but its a medium size school, electrical installation is in a reasonable state, approx 35 years old in oldest areas, circuits mostly labelled, gets tested every 5 yearsreguarly apparently so i dont hopefully foresee many big problems
11 single phase boards between 6-12 way
12 three phase boards between 4-12 way
1no. MCCB panel board 4 way
Approx 280 individual circuits
Apparently previous paper work is availiable
Work will be undertaken between 3-6pm one or two days per week until complete
Much appreciated?
I know its difficult without visiting site but its a medium size school, electrical installation is in a reasonable state, approx 35 years old in oldest areas, circuits mostly labelled, gets tested every 5 yearsreguarly apparently so i dont hopefully foresee many big problems
11 single phase boards between 6-12 way
12 three phase boards between 4-12 way
1no. MCCB panel board 4 way
Approx 280 individual circuits
Apparently previous paper work is availiable
Work will be undertaken between 3-6pm one or two days per week until complete
Much appreciated?