What do you guys do after rectification of defects listed on an EICR.

Reinspect the installation and issue a new EICR? Do you charge for the inspection again?
Issue a new EICR?
Fill out a MW or EIC for the rectifications and provide with the 1st EICR?
 
Issue relevant certificates and LABC notifications if applicable for the works and then re issue EICR is what I do. Depending on how far they have gone with the remedial works getting done they may still have C3's on there!
 
Sometimes i rectify as im going along, if its nothing major.

Normally though, i issue the EICR with unsatisfactory, then a new EICR when the rectification work has been done again.

Charge rectification fee, not the price of a full EICR. If it's major rectification work, or a considerable amount it could cost more than the EICR anyway.
 
Depending how much work was required I'd issue MW(s) or EIC stating scope being repairs following EICR serial no .......
No need to reissue EICR in my opinion...
 
Same as mark. Issue a new satisfactory report when the remedials have been carried. The companies we work for need this for their insurance so need a report with a satisfactory on as this gets checked.
 
I don't issue an unsatisfactory report straight away, I give a list of c2 and c1 and costs of remedial work, explain the situation that they have 3 options, 1 do nothing 2 get another spark in to carry out remedial work which I will inspect or 3 I do the remedials and issue satisfactory report

Only once have I have I issued unsatisfactory
 
Sometimes i rectify as im going along, if its nothing major.

Normally though, i issue the EICR with unsatisfactory, then a new EICR when the rectification work has been done again.

Charge rectification fee, not the price of a full EICR. If it's major rectification work, or a considerable amount it could cost more than the EICR anyway.


Each to there own on this one but I generally issue MWC or EIC for the remidial works that need doing and these, along with the previous EICR should show that the work has been carried out and the instaaltion is now satisfactory.

Now, if the customer wants another EICR doing that shows satisfactory, then of course I would do it and charge them again. But you would still have to issue MWC or EIC for the remidial works you have carried out.
 
Best EV Chargers by Electrical2Go! The official electric vehicle charger supplier.

OFFICIAL SPONSORS

Electrical Goods - Electrical Tools - Brand Names Electrician Courses Green Electrical Goods PCB Way Green 2 Go Pushfit Wire Connectors Electric Underfloor Heating Electrician Courses Heating 2 Go
These Official Forum Sponsors May Provide Discounts to Regular Forum Members - If you would like to sponsor us then CLICK HERE and post a thread with who you are, and we'll send you some stats etc

Advert

Daily, weekly or monthly email

Thread starter

Joined
Location
Preston, Lancashire

Thread Information

Title
EICR retification.
Prefix
N/A
Forum
Periodic Inspection Reporting & Certification
Start date
Last reply date
Replies
6

Advert

Thread statistics

Created
ste mac,
Last reply from
Jay Sparks,
Replies
6
Views
3,445

Advert

Back
Top