Ive recently qualified and taken on a fairly big job (for me anyway) in a flat which includes:
1. CU change - from rewireable to 4 way with 4 x rcbos
2. New ring cct for relocated kitchen plus washing machine and tumble dryer in hallway
3. New cooker cct for hob and oven
4. Moving 2 double sockets on existing ring
5. Installing PIR light in front yard...
...am i right in thinking that i need to complete a EIC for the two new ccts and 2 x MW certs for the work on the existing ring and lighting ccts?
Thanks in advance for any help with this