Hi, doing a garage conversion into habitable room and will have to move the CU.
Currently it's at high level above the entry where the meter tails come through the wall.
The CU needs to be moved to make way for a doorway and will be fitted approx 6M from existing position on the other side of the doorway.
The floor is to be raised 100mm to make level with existing house floor level and the walls are to be battened out and plasterboarded.
Question, would it be best to run the new supply in SWA down the wall and under the new floor and back up to new CU, or use new tails in 50mm X 50mm trunking down the wall and under the new floor.
I'm fitting a 100A fused switch as the tails will be greater than 3M long.
just looking for pro's and con's for each method.
Thanks
Currently it's at high level above the entry where the meter tails come through the wall.
The CU needs to be moved to make way for a doorway and will be fitted approx 6M from existing position on the other side of the doorway.
The floor is to be raised 100mm to make level with existing house floor level and the walls are to be battened out and plasterboarded.
Question, would it be best to run the new supply in SWA down the wall and under the new floor and back up to new CU, or use new tails in 50mm X 50mm trunking down the wall and under the new floor.
I'm fitting a 100A fused switch as the tails will be greater than 3M long.
just looking for pro's and con's for each method.
Thanks