I was asked to wire up a boiler / pump / valve / 2 channel 7 day programmer / frost stat (no room stat) today
"connect the boiler up, its a Y plan"
However it has caused me some confusion.
The valve has the following connections over 2 seperate flexes
On one flex- blue (neutral) brown (clockwise) black (counter clockwise) (brown/black might be the other way around I don't have it with me)
On another flex, an orange, red and white cores, which are C, NC and NO.
(sorry, I can't remember the exact connections colours but basically, N, CW, CCW, C, NC, NO)
How do I implement this valve into the system? Am I missing something?
I'm fine following a diagram- if there was one, but I don't seem to be able to figure this out!
If it made any odds, the pump is fed via the boiler which has an overrun
"connect the boiler up, its a Y plan"
However it has caused me some confusion.
The valve has the following connections over 2 seperate flexes
On one flex- blue (neutral) brown (clockwise) black (counter clockwise) (brown/black might be the other way around I don't have it with me)
On another flex, an orange, red and white cores, which are C, NC and NO.
(sorry, I can't remember the exact connections colours but basically, N, CW, CCW, C, NC, NO)
How do I implement this valve into the system? Am I missing something?
I'm fine following a diagram- if there was one, but I don't seem to be able to figure this out!
If it made any odds, the pump is fed via the boiler which has an overrun