Just wondering what the whole procedure is? What are the rules and regs associated with this etc? Whats the situation if your having a single phase or three phase board?

Thanks in advance. :) John
 
Re: Whats the process with running a new electricity supply from i.e EDF to fuseboard

1: Apply to DNO for supply ( application for supply will be sent to you , you will proberbly need help to
fill in the form )
2: Appoint an electrical contractor to carry out new installation.( He will fill in
the form and ask you to sign it and return to DNO)
3: Contractor will then liase with DNO regarding connection, complition and certification of the new
installation)
4: Contractor will arrange connection
5: You pay contractor ( if you have not already done so)

Simples:D
 

OFFICIAL SPONSORS

Electrical Goods - Electrical Tools - Brand Names Electrician Courses Green Electrical Goods PCB Way Green 2 Go Pushfit Wire Connectors Electric Underfloor Heating Electrician Courses Heating 2 Go
These Official Forum Sponsors May Provide Discounts to Regular Forum Members - If you would like to sponsor us then CLICK HERE and post a thread with who you are, and we'll send you some stats etc

Advert

Daily, weekly or monthly email

Thread Information

Title
Whats the process with running a new electricity supply from i.e EDF to fuseboard?
Prefix
N/A
Forum
Australia
Start date
Last reply date
Replies
1
Unsolved
--

Advert

Thread statistics

Created
cairns,
Last reply from
bugsy,
Replies
1
Views
2,442

Advert

Back
Top