Mark.W
-
Hey Guys,
Just wondering how you guys are costing and marking up your jobs.
What I am currently doing is a 20% markup on materials and 20% on labour, and then with regards to Overheads I have a formula as follows:
Eg:
If I require £900/month to keep my business afloat and there is on average 21 working days in a month, I divide 900 by 21 to give me a daily O/H cost of £42.85.
I then work out how long the job is expected to take and multiply it by my hourly rate/daily rate.
So I end up with...
Materials incl Vat +20%MU
+ (Labour + 20%MU)
+ O/H
These added together give me my sell value.
It seems to work for me just wondering what you guys are doing?
Cheers
Mark
Just wondering how you guys are costing and marking up your jobs.
What I am currently doing is a 20% markup on materials and 20% on labour, and then with regards to Overheads I have a formula as follows:
Eg:
If I require £900/month to keep my business afloat and there is on average 21 working days in a month, I divide 900 by 21 to give me a daily O/H cost of £42.85.
I then work out how long the job is expected to take and multiply it by my hourly rate/daily rate.
So I end up with...
Materials incl Vat +20%MU
+ (Labour + 20%MU)
+ O/H
These added together give me my sell value.
It seems to work for me just wondering what you guys are doing?