Part of the G83 Apprendix 3 commissioning form asks for the Generator Test Report (Appendix 4). This I assume is the test(s) done by the manufacturer to make sure their product complies, in which case we don't have to supply this to the DNO? Is that correct?
 
I think you do have to supply it. Central Networks have specifically asked me for a copy of the type test certificate for the inverter on an install I am doing. You can download a copy of the certificate from manufacturers' websites normally.

Regards
Bruce
 

OFFICIAL SPONSORS

Electrical Goods - Electrical Tools - Brand Names Electrician Courses Green Electrical Goods PCB Way Green 2 Go Pushfit Wire Connectors Electric Underfloor Heating Electrician Courses Heating 2 Go
These Official Forum Sponsors May Provide Discounts to Regular Forum Members - If you would like to sponsor us then CLICK HERE and post a thread with who you are, and we'll send you some stats etc

Advert

Daily, weekly or monthly email

Thread starter

Joined
Location
Dorset

Thread Information

Title
G83 Commissioning Form
Prefix
N/A
Forum
Solar PV Forum | Solar Panels Forum
Start date
Last reply date
Replies
4

Advert

Thread statistics

Created
yellowvanman,
Last reply from
GreggElectrical,
Replies
4
Views
4,752

Advert

Back
Top