So I’ve completed my Level 3 302 exam and got a Distinction. I’m just starting my project now. It’s a Pool, Hotel Rooms and Dining Room/Kitchen.

Seem okay so far. Any advice from people that have done it?
 
Design it as if you’re installing it. Keep it as simple as possible, diversity is king, no expense spared, use technology such as smart switching, swap incandescent lighting etc for LED to save the planet and reduce demand, this list is endless.
 
Thanks for the advice. I’m just working on Q1. Which is circuit diagram, three phase supply system and earring arrangements from substation to transformer to charging unit. It should show the total earth fault loop for the charging unit.

Diagram needs to indicate connection points for each item of equipment.


So I am thinking 3 phase with an MCB or CCU, then goes into the EVC Unit. The EVC unit will have its earth TT system. Which I think is in the 18th Edition.

I’m going to draw it out on scrap paper. Any other suggestions?
 

OFFICIAL SPONSORS

Electrical Goods - Electrical Tools - Brand Names Electrician Courses Green Electrical Goods PCB Way Green 2 Go Pushfit Wire Connectors Electric Underfloor Heating Electrician Courses Heating 2 Go
These Official Forum Sponsors May Provide Discounts to Regular Forum Members - If you would like to sponsor us then CLICK HERE and post a thread with who you are, and we'll send you some stats etc

Advert

YOUR Unread Posts

Daily, weekly or monthly email

Thread starter

RDB85

Trainee
-
Joined
Location
Liverpool
If you're a qualified, trainee, or retired electrician - Which country is it that your work will be / is / was aimed at?
United Kingdom
What type of forum member are you?
Trainee Electrician

Thread Information

Title
Level 3 Project - Advice
Prefix
N/A
Forum
UK Electrical Forum
Start date
Last reply date
Replies
10
Unsolved
--

Advert

Thread statistics

Created
RDB85,
Last reply from
RDB85,
Replies
10
Views
1,669

Advert

Back
Top