Hi Chaps, I posted a thread a couple of weeks ago about a scrap I was having with a builder, well today it's taken an even more interesting turn and I'm starting to doubt myself, which is never a good look.
Basically: the build is a mess, unhappy client, builder with very dubious financial history. Client is going to throw the builders off site next week (plus I go away to the States on hoilday) so it's all hands to the pumps to get the thing finished. I've got a couple of days worth of final snagging and odds and sods then I'm good to sign off so far, then return to do even more after Easter.
Original job was won on tender (£11.5k+vat) and with extra's it's now running to about £18K +vat. So far I have only managed to collect £8k INC, so I'm getting very twitchy (especially as this morning it was discovered that the builders plumber has made a cock-up of biblical proportions which will probably result in them getting fired even earlier) . Further work after Easter will see it running at nearly £25k so it's turned into a nice bit of work, thank you. Now, the client and I are on the same side, and both of us are equally fed up with the builder and having lots of discussion behind the scenes. Builder claims to have no knowledge of my balance invoice for £8k due midday today (allowing for a fair retention, I'm very good like that) despite having acknowledged receipt of the email it was sent on two weeks ago.
So I've thrown my toys out of the pram and am taking the 'goods are mine until payment' approach, so this afternoon (after the builder wouldn't return my calls) I started to remove my goods.......or to be more precise I left site having taken the primary bus bar out and placed it on the passenger seat on the van. Oddly enough, half an hour later as it dawned on all the chippies that the site was dead, I started to get some calls back.
From that point on it gets ugly, but I'm standing my ground. Am I right?
Basically: the build is a mess, unhappy client, builder with very dubious financial history. Client is going to throw the builders off site next week (plus I go away to the States on hoilday) so it's all hands to the pumps to get the thing finished. I've got a couple of days worth of final snagging and odds and sods then I'm good to sign off so far, then return to do even more after Easter.
Original job was won on tender (£11.5k+vat) and with extra's it's now running to about £18K +vat. So far I have only managed to collect £8k INC, so I'm getting very twitchy (especially as this morning it was discovered that the builders plumber has made a cock-up of biblical proportions which will probably result in them getting fired even earlier) . Further work after Easter will see it running at nearly £25k so it's turned into a nice bit of work, thank you. Now, the client and I are on the same side, and both of us are equally fed up with the builder and having lots of discussion behind the scenes. Builder claims to have no knowledge of my balance invoice for £8k due midday today (allowing for a fair retention, I'm very good like that) despite having acknowledged receipt of the email it was sent on two weeks ago.
So I've thrown my toys out of the pram and am taking the 'goods are mine until payment' approach, so this afternoon (after the builder wouldn't return my calls) I started to remove my goods.......or to be more precise I left site having taken the primary bus bar out and placed it on the passenger seat on the van. Oddly enough, half an hour later as it dawned on all the chippies that the site was dead, I started to get some calls back.
From that point on it gets ugly, but I'm standing my ground. Am I right?
Last edited: