We have installed a lot of Powerwall 1's and 2's. They do seem to work very well. We have customers now only importing less than 0.4KWh most days.
Most customer do not have EV's, but they are at work all day when the solar is being generated. This way when they get home all their solar has been...
HI all,
We have a customer who has 2 x 50 kWp solar arrays (one with SMA inverters; the other Delta) with a 50 kW export limit.
He currently has a Cluster Controller / Energy Meter set up and working fine to limit one of his 50 kWp arrays (SMA) to zero export.
The customer would now like to move...
there are a few photos of the power walls installed on our Facebook page here Infinity Energy Services Ltd | Facebook - https://www.------------/InfinityEnergyLtd/
or our website, Infinity Energy Services
Yes we have installed around 15 of them. Its a nice enjoyable job actually, can be challenging manoeuvring it around as it weighs 100Kgs
Have done variety of SolarEdge and AC coupled SMA versions. SMA had said off peak charging would be available by the end of last year via a software update but...
HI all,
We have a customer who has 2 x 50 kWp solar arrays (one with SMA inverters; the other Delta) with a 50 kW export limit.
He currently has a Cluster Controller / Energy Meter set up and working fine to limit one of his 50 kWp arrays (SMA) to zero export.
The customer would now like to...
Its not just large companies, we became accredited and were small, its probably down to your PV experience as you would need to be MCS accredited at a minimum.
I'm in desperate need of an RS485 Extension kit for. Solaredge inverter.If anyone has one they could sell me or know of anyone it would be massively appreciated!
Thanks.
Go online and get small claims court involved.
I done it recently customer owed me £74 kept saying she would send money and never did, it's more the principle as it was 120days overdue! Takes about 20mins to do and add the £25 cost to the bill plus interest. It will get them moving if they...
Dont forget with DNO cable the phase will be aluminium 25mm and the neutral will be the twisted copper around the outside of it. So looks much smaller.
I know as used to work for SSE and installed quite a few into new flats etc
No we ordered one last week. They send the replacement out and you swap if. Takes about a month to arrive!
Had An SMA 10000tl pack in last week. Called SMA, replacement arrived next day!
I think the whole thing is a joke. Another example of the government taking from the small time investers. Why should they take more in tax than someone will earn from. Property they have invested in.
You work hard- your taxed hard. Then with the money you have been taxed on you buy a buy to...
These Official Forum Sponsors May Provide Discounts to Regular Forum Members - If you would like to sponsor us then CLICK HERE and post a thread with who you are, and we'll send you some stats etc
Sure, ad-blocking software does a great job at blocking ads, but it also blocks useful features of our website. For the best site experience please disable your AdBlocker.