stubo300

i am quoting to install a 3.80kwp system on a old farm house, do i need to contact the DNO as it is the only house which will have it installed.

and as it is going to be installed on the house roof and connected to the domestic supply will that get the 41.3 fits
 
Contact the DNO on the day of connection, then you have 30 days to submit your paperwork, the will qualifie for the FITS providing you are MCS.
 
If your system can, in theory, send >3.68kW onto the grid then they need prior notification. ALL systems need notification of some kind.
 
As stated >3.68kW or >16Amps Needs prior notification under G83/1. All installations need Post notification.
 

Similar threads

OFFICIAL SPONSORS

Electrical Goods - Electrical Tools - Brand Names Electrician Courses Green Electrical Goods PCB Way Electric Underfloor Heating Electrician Courses Heating 2 Go Electrician Workwear Supplier
These Official Forum Sponsors May Provide Discounts to Regular Forum Members - If you would like to sponsor us then CLICK HERE and post a thread with who you are, and we'll send you some stats etc

Advert

Daily, weekly or monthly email

Thread Information

Title
do i have to contact the DNO
Prefix
N/A
Forum
Solar PV Forum | Solar Panels Forum
Start date
Last reply date
Replies
3

Advert

Thread statistics

Created
stubo300,
Last reply from
ESP,
Replies
3
Views
2,970

Advert