Hi Gents
EDF ask me for death test before they connect el. meter.
What they mean?
Thanks
 
Dead tests m8. Its all the readings taken from the circuits within the house such as R1+R2, insulation resistance etc before it's energized you will have to issue them with an installation cert or periodic before they will connect up the power, they want proof that what they are connecting up to is safe.
 
Last edited by a moderator:
Just reading about this very subject (sorry vid from the niceic ) and above absolutely correct of course, Do all your tests and record on the actual certificate that you will finally issue. Apparently they will accept a partially completed certificate as enough evidence the installation is safe to connect to, you can then do the live tests on the same certificate. Job done.

Actually, I rather like the idea of a death test. Could be a new way of testing RCDS, or if re wirables have the correct fuse wire in them. There could be a mini course in how to do them, actualy best if i shut up.
 
Last edited by a moderator:

Similar threads

OFFICIAL SPONSORS

Electrical Goods - Electrical Tools - Brand Names Electrician Courses Green Electrical Goods PCB Way Electric Underfloor Heating Electrician Courses Heating 2 Go Electrician Workwear Supplier
These Official Forum Sponsors May Provide Discounts to Regular Forum Members - If you would like to sponsor us then CLICK HERE and post a thread with who you are, and we'll send you some stats etc

Advert

Daily, weekly or monthly email

Thread Information

Title
Death test
Prefix
N/A
Forum
Periodic Inspection Reporting & Certification
Start date
Last reply date
Replies
5

Thread Tags

Tags Tags
death test

Advert

Thread statistics

Created
Sly,
Last reply from
marksparky,
Replies
5
Views
1,772

Advert