I know this has been kicked around quite a bit on the forum but I have not seen any answer in terms of solid regs or otherwise. i.e. no compelling reason to fit, or leave it as is.
29 Units have Merlin Gerin boxes. All supplied from switch room by MCCB. Various sizes of SWA. 3 core L-N-E. Armour is terminated on DB (Merlin Gerin again) without banjo or fly lead onto earth busbar. This then goes to Ring CCT and lighting CCT in each Unit.
Question. Should we supply banjo and fly leads and fit them?
with reasons why (or why not) On an EICR what code would you give absence of fly leads (bonus question)
29 Units have Merlin Gerin boxes. All supplied from switch room by MCCB. Various sizes of SWA. 3 core L-N-E. Armour is terminated on DB (Merlin Gerin again) without banjo or fly lead onto earth busbar. This then goes to Ring CCT and lighting CCT in each Unit.
Question. Should we supply banjo and fly leads and fit them?
with reasons why (or why not) On an EICR what code would you give absence of fly leads (bonus question)