Hello All

Iam installing a Small 8kva UPS we are ruuning a 50A supply to a sub board in the comms room where the UPS is then we we supply the UPS from that sub board.

When testing Continuity R1 R2 on a 3 phase supply can i just test from the live conductors to earth 1 ant a time and note the highest reading or is it easier to either link the L1 L2 L3 together.

Also iam not to keen in carrying out an IR test on the CCT supplying the UPS could i put this down as LIM and carrying out an IR test on the new supply cable supplying the new sub board.

Thanks

James
 
Do your continuity on each phase separately, if you think about it you will work out why you shouldn't do them all connected together.

You should IR the complete circuit before you wire the UPS into it.

Cheers............Howard
 

Similar threads

OFFICIAL SPONSORS

Electrical Goods - Electrical Tools - Brand Names Electrician Courses Green Electrical Goods PCB Way Electric Underfloor Heating Electrician Courses Heating 2 Go Electrician Workwear Supplier
These Official Forum Sponsors May Provide Discounts to Regular Forum Members - If you would like to sponsor us then CLICK HERE and post a thread with who you are, and we'll send you some stats etc

Advert

Daily, weekly or monthly email

Thread Information

Title
Advice needed please ups systems
Prefix
N/A
Forum
Periodic Inspection Reporting & Certification
Start date
Last reply date
Replies
2

Advert

Thread statistics

Created
James Sutton,
Last reply from
James Sutton,
Replies
2
Views
836

Advert