Afternoon chaps
Just had a quick call from one of my builders.
Job was house refurb+ full rewire- local to me. I worked through builder- who worked for client.
I had it all 1st fixed apart from kitchen power and lighting and dining lighting
(was waiting for dividing wall to be knocked down and steel to go in for open plan)
-although I had all the feeds over to the kitchen ready to go.
Payment plan was 25% after I done what I have done ^^ -which I have been paid
Then 25% after I 1st fixed kitchen -obviously not done yet
Then remaining 50% o completion.
Just said hes had another argument with client and he is walking. For me to have a sit down and think what he owes me (if anything) and he will call me later.
- do trust the builder- so don't think he is doing the dirty on me.
-not sure if I will get the job back direct from the client- as he was pretty happy with my work and I did deal with him a few times (email and face to face) regarding positions and socket finish etc- so there is a possibility I might..... (not sure if builder will mind though!!)
How would you go about working out what I am owed....
minus the cost of the whole kitchen
minus the cost of 2nd fix materials
how would you work out labour cost of 2nd fix to minus?
-although I quoted per point- say it would roughly take me 2days to 2nd fix- so minus 2days worth of day rate too?
looking for advise really as still young at 24 and never had this before so bit unsure!!!
Just had a quick call from one of my builders.
Job was house refurb+ full rewire- local to me. I worked through builder- who worked for client.
I had it all 1st fixed apart from kitchen power and lighting and dining lighting
(was waiting for dividing wall to be knocked down and steel to go in for open plan)
-although I had all the feeds over to the kitchen ready to go.
Payment plan was 25% after I done what I have done ^^ -which I have been paid
Then 25% after I 1st fixed kitchen -obviously not done yet
Then remaining 50% o completion.
Just said hes had another argument with client and he is walking. For me to have a sit down and think what he owes me (if anything) and he will call me later.
- do trust the builder- so don't think he is doing the dirty on me.
-not sure if I will get the job back direct from the client- as he was pretty happy with my work and I did deal with him a few times (email and face to face) regarding positions and socket finish etc- so there is a possibility I might..... (not sure if builder will mind though!!)
How would you go about working out what I am owed....
minus the cost of the whole kitchen
minus the cost of 2nd fix materials
how would you work out labour cost of 2nd fix to minus?
-although I quoted per point- say it would roughly take me 2days to 2nd fix- so minus 2days worth of day rate too?
looking for advise really as still young at 24 and never had this before so bit unsure!!!