I am just checking through the information I need to enter for the UKPN SmartConnect site following the commissioning of my PV/Battery system, this is a G99 system and I have approval from UKPN.
Most of it is clear however I am not sure what I need to provide to answer this question ' Proof that Site Compliance and Commissioning test requirements for Type A Power Generating Modules are fulfilled as per Form A2-4'
I don't have a Form A2-4 for my inverter, I do have the ENA form A2-3.
The new system has been tested by me and my electrician.
Does anyone know how I should answer this question?
Thanks
Most of it is clear however I am not sure what I need to provide to answer this question ' Proof that Site Compliance and Commissioning test requirements for Type A Power Generating Modules are fulfilled as per Form A2-4'
I don't have a Form A2-4 for my inverter, I do have the ENA form A2-3.
The new system has been tested by me and my electrician.
Does anyone know how I should answer this question?
Thanks