I was asked which tests during a Schedule of test on a new building and then on an in use building were mandatory.
Where ever I look in the few regs books I have with me they say where "relevant" or "recommended" not will be or shall be done!

So,..... R2 test mandatory or if you feel like it, same with Insulation Testing, is it down to how you feel on the day ?!

Anyone have an Approved reference they can point me towards that says this test WILL BE DONE ?

Thanks
 
on a new build, do all the tests as laid out on the SOTR. for an existing installation, testing is limited to what you and the client agree on. obviously, the more N/Vs you put on an EICR, the less value the document has.
 
But what about a building 10 years old, and where does it say YOU WILL !

Make up your own cert and have titles like 'Light switch works'.....
That would then be an EICR, you discuss with the client how far the testing will go and explain this on the pages when it asks for clarification of what has been agreed.
 
all down to how big your writing is, and how much you can fit on the back of a beermat. (or smoke packet for the teetotallers).
 
But what about a building 10 years old, and where does it say YOU WILL !

Make up your own cert and have titles like 'Light switch works'.....

Eh? It doesn't matter how old the building is. If you are doing an actual job then you will be issuing a cert with a schedule of tests, which must be done or else how can you issue it? As for an EICR on such an installation, well I personally test 100% of circuits, again I couldn't fill out the EICR without doing so!
 
on a new build, do all the tests as laid out on the SOTR. for an existing installation, testing is limited to what you and the client agree on. obviously, the more N/Vs you put on an EICR, the less value the document has.

I said that the SOTR in the Regs would be the minimum required but I can't find anywhere where it states THESE are the minimum that YOU MUST do, all I could find was "Recommended"!!
 

Reply to Schedule of Test.... are any mandatory? in the Periodic Inspection Reporting & Certification area at ElectriciansForums.net

Similar Threads

I got a TEXT message (i dont know them and i cant find out who they are from the phone number) "Hi speaking from Indeed Are you available to give...
Replies
15
Views
929
Hello fellow sparks, I’m looking to do my testing and inspection course which starts on the 30th of April, but I have not got much testing...
Replies
0
Views
275
Hi, I have a book on domestic wiring which says that everywhere there is a change in current carrying capacity along a circuit there must be some...
Replies
3
Views
304
Hi, while testing the new board I installed I got to the live testing at the sockets one of the RCD's kept tripping during the loop test, the...
Replies
4
Views
1K
Now Ive done Periodic Inspection and Initial Virification Qualifications with LCL/EAL (so non C&G 2394/95) # strange part building Modules , this...
Replies
6
Views
998

OFFICIAL SPONSORS

Electrical Goods - Electrical Tools - Brand Names Electrician Courses Green Electrical Goods PCB Way Electrical Goods - Electrical Tools - Brand Names Pushfit Wire Connectors Electric Underfloor Heating Electrician Courses
These Official Forum Sponsors May Provide Discounts to Regular Forum Members - If you would like to sponsor us then CLICK HERE and post a thread with who you are, and we'll send you some stats etc

YOUR Unread Posts

This website was designed, optimised and is hosted by untold.media Operating under the name Untold Media since 2001.
Back
Top