Came across this on an EICR and was wondering how everyone else would code it. Basically there’s a sangamo time clock that controls a contactor which switches a 3 phase DB for storage heaters, strange set up in a flat. So you’ve basically got 6mm cables in this sangamo time clock that are protected by the supply authority fuse, would you code that a c2? Main fuse is 100a. Would be better if this was being supplied from an mcb I would say