I don't think it would help the OP Murdoch as he's from Northern Ireland which have a different set of building regs. Technical Booklets 2012 ? Building Control NI A quick look through technical document R page 46 and I think they have different requirements on heights of accessories for example.

How stupid can the UK get. Surely 1 set of regs would be best.... no wonder the incomers get confused then don't give a txss!
 
Generally if your registered in Ireland, it's normally NICEIC or ECA in Northern Ireland or RECI in Southern Ireland
The black connectors your are referring to are , and this is where the spark would generally disconnect the tails when they are carrying out a consumer unit change, but its work that need to be carried out with a bit of care when you are working live
 
Generally if your registered in Ireland, it's normally NICEIC or ECA in Northern Ireland or RECI in Southern Ireland
The black connectors your are referring to are , and this is where the spark would generally disconnect the tails when they are carrying out a consumer unit change, but its work that need to be carried out with a bit of care when you are working live

Thats the correct thing Martin, I am going to buy a REC 2 100amp Isolating switch tomorrow, call NIE and get them to isolate the house supply to enable me to do the switch over or let them do it for me, save a lot of hastle in the future if these amendments keep changing !! Or does NIE provide REC 2 switch upon request?
 
I haven't been involved in domestic as a rule but
Generally a competent spark would disconnect the tails from the Isco's , and carry out the consumer unit change without involving the NIE , as the demarcation line from the NIE is normally the tails going into the meter
 
Not sure what you meant about only registering with RECI and the 1st of January, in regards to a northern contractor

I didn't mention northern contractors. I was saying that since the 1st January RECI has been the only Electrical Safety Supervisory Body (SSB) in the south, and therefore it has only been possible to be registered with RECI in the south. The other SSB was registering anyone and everyone and therefore the Commission for Energy Regulation (CER) put out to tender that there would only be one SSB.

RECI won the tender and the other SSB only came third. (An outside company came second.) Therefore RECI is the only show in town in the south now.

In the north it is still NICEIC Approved Contractor and ECA. (I think there may be something like one NAPIT member in the north.)
 
Last edited:
I haven't been involved in domestic as a rule but
Generally a competent spark would disconnect the tails from the Isco's , and carry out the consumer unit change without involving the NIE , as the demarcation line from the NIE is normally the tails going into the meter


...thus falling foul of EAWR Regulation 14.
 
I am currently planning on changing the Consumer Unit in the Boiler Room of my home. The board is 17 years old, fitted with old cartridge fuse holders. I am planning on upgrading to a new amendment 3 (bs7671 - 2015) standard. The problem I am having is that I have no experience of working Live, the incoming tails from the meter box have no means of isolation. They are connected into Black connector blocks just before the Consumer Unit and then doubled together in both connectors and are connected on til 2 80A RCD's. If I can get the tails safely isolated, I know how to do all the rest.
Can anybody here advise me on what my safest option would be to give me peace of mind?

First year Trainee Oggymac, I wouldn't have thought that you have the experience to do this work on your own, maybe you could attempt it under the supervision of your mentor
 
...thus falling foul of EAWR Regulation 14.
not in my book. if all precautions to prevent injury are taken, there's no reason to hold a job up several days to wait for someone else to wander up and work live, same as you would do yourself.
 
Call your supplier and get them to fit an isolator switch. Then call your local building control, tell them what you want to do and they will check over it all for you and sign it off if satisfactory. This all costs money though..
 
not in my book. if all precautions to prevent injury are taken, there's no reason to hold a job up several days to wait for someone else to wander up and work live, same as you would do yourself.


Npw, you know that's not what the reg says, it's only one of three prerequisites. I'd love to have you argue in court that it was unreasonable to make the conductor dead.
 
not in my book. if all precautions to prevent injury are taken, there's no reason to hold a job up several days to wait for someone else to wander up and work live, same as you would do yourself.

When making it dead is as simple as pulling the bullet then it is unreasonable to work live don't you think?
 
How stupid can the UK get. Surely 1 set of regs would be best.... no wonder the incomers get confused then don't give a txss!

It's getting worse - I notice that AM3 OSG talks about the "Building Regulations of Wales" (OSG section 1.2.4) - "On 31 December 2011 the power to make building regulations for Wales was transferred to Welsh Ministers".

It says that the building regs for England and Wales continue to apply in Wales until Welsh Minsters make changes to them.
 
It's getting worse - I notice that AM3 OSG talks about the "Building Regulations of Wales" (OSG section 1.2.4) - "On 31 December 2011 the power to make building regulations for Wales was transferred to Welsh Ministers".

It says that the building regs for England and Wales continue to apply in Wales until Welsh Minsters make changes to them.

That doesn't seem to make sense to you? What regulations should apply until Welsh ministers make changes to them?
 

Reply to Changing Consumer Unit in the Electrical Wiring, Theories and Regulations area at ElectriciansForums.net

Similar Threads

Hi, I have a job for a customer, the consumer unit is an old 3036 board and there are several holes in it giving access to live parts, I can...
Replies
6
Views
702
Ok, most new Consumer unit seem to come with a 63A RCCB and two MCBs. Most house consumer units now will also have RCD of some type be it a dual...
Replies
24
Views
1K
I wondered if it is OK to have 2 x Main Switches in the same consumer unit. One feeding the RCBOs in the House and one feeding the CU in a garage...
Replies
16
Views
774
hello all...whats the typical cost for a new consumer unit fitted and the old wired fuse box removed im in a semi detached house in...
Replies
2
Views
248
I am planning to go semi off grid with a victron and battery system. The system will be installed in an out building about 20 meters away from...
Replies
7
Views
744

OFFICIAL SPONSORS

Electrical Goods - Electrical Tools - Brand Names Electrician Courses Green Electrical Goods PCB Way Electrical Goods - Electrical Tools - Brand Names Pushfit Wire Connectors Electric Underfloor Heating Electrician Courses
These Official Forum Sponsors May Provide Discounts to Regular Forum Members - If you would like to sponsor us then CLICK HERE and post a thread with who you are, and we'll send you some stats etc
This website was designed, optimised and is hosted by Untold Media. Operating under the name Untold Media since 2001.
Back
Top
AdBlock Detected

We get it, advertisements are annoying!

Sure, ad-blocking software does a great job at blocking ads, but it also blocks useful features of our website. For the best site experience please disable your AdBlocker.

I've Disabled AdBlock