I have a question regarding isolation and switching arrangements.

I want to work out what would work best within the regulations regarding splitting a new 200a TPN PME supply to serve flats above and a shop below.

my initial thinking new 200a PME supply - Trunking above feeding a new ryefield giving me x2 100a 3 phase supplies. (2x100a 3 phase supplies)
I would then have a x2 100a un- fused isolators for the shop and flats

*will i need an isolator between the Ryefield and the service head
*does the above sound feasible?
 
OP
C

chris day

London Sparks
Messages
383
Location
london
there is already a Ryefield up stream with x4 45a S-Phase supplies for each flat respectively
 

buzzlightyear

please let me back in to the prison cell.
Electrician's Arms
Messages
6,982
Location
star command
there is already a Ryefield up stream with x4 45a S-Phase supplies for each flat respectively
not three phase then ,you need to up grade the s/phase to 3phase cause of loading ,speak to you client and let them speak to the DNO .
 

Nebu1a

Regular EF Member
Messages
99
Location
Hampshire
Sounds like you are being the BNO. UK power networks have a good guide on this as I have been in a similar situation. Make sure you are in contact with the DNO and what their requirements are. Some DNOs may ask for a 3 phase isolator before the ryefield. If its a small install you may get away without one. I fitted switch fuses to my risers.
 

Permanent unswitched live colour?

  • Brown

    Votes: 60 66.7%
  • Black

    Votes: 30 33.3%