Hi, please can someone confirm whether lights and pull switches etc out with zones 0,1 and 2 in bathrooms require to be included in the supplementary bonding?
I understand the basics and in this instance only the new shower will be 30mA protected, the lights and down flow are out with the zones and will only be 100mA protected.
So is it acceptable to omit the lighting pullcord, light and down flow from the supplementary bonding or must they be bonded? I suspect to work to the regs they should be bonded but wanted to confirm this, any help appreciated