I have just completed a (large) new build timber lodge in a customers (large) rear garden and today given it a full test and produced an EIC for it.

The owner says he has not needed building control/planning consent as it is just within the criteria to not need it, even though it is a 4 bed, 60' x 22' lodge!

My question is, as the lodge does not come under building control, do I need to notify them of the electrical part of the job?

This may sound an obvious question to most, but I have not come across this situation before. My thought is that as it is a new build, I will have to notify.

Any thoughts?
 
Sounds so simple when you put it like that.
I think i was overthinking it and doubting myself and getting mixed up with the fact that the lodge doesn't come under planning consent.
Now I feel a ---- for asking such a simple question!
Cheers
 
You could argue a 'lodge' is not a dwelling and if you can argue its not a 'dwelling' then Part Pee need not apply.

When does a lodge go from being just a lodge to a dwelling ?
 
You could argue a 'lodge' is not a dwelling and if you can argue its not a 'dwelling' then Part Pee need not apply.

When does a lodge go from being just a lodge to a dwelling ?

even though it is a 4 bed, 60' x 22' lodge!

It has 4 beds in it, so its a dwelling, in my eyes.
 
  • Like
Reactions: Jim_e_Jib
New supply from a circuit in the main house, which will be a dwelling.
 
The scope of part P includes outbuildings such as sheds etc, I'm confident that this would be included
 
  • Like
Reactions: Jim_e_Jib and DPG
My understanding is that Part P applies to anything fed from one electricity meter if that meter is in a dwelling, or if the meter is not in a dwelling, but serves a dwelling amongst other things.
On the other hand, isn't it the householders obligation to do the notifying, not the electrician, although they normally do this on the householder's behalf?
 
The owner says he has not needed building control/planning consent as it is just within the criteria to not need it
Sounds like he might be trying to pull a fast one, if as PM and others say new circuits, new CU etc it requires a notification all day long!
By notifying it you might just 'drop him in it' but thats his problem not yours, you are just doing your job.
 
  • Like
Reactions: Jim_e_Jib
Sheds or outbuildings need planning permission if they over a certain height, there might be other criteria too. Not that has anything to do with notification of electrics !
 

Similar threads

OFFICIAL SPONSORS

Electrical Goods - Electrical Tools - Brand Names Electrician Courses Green Electrical Goods PCB Way Electric Underfloor Heating Electrician Courses Heating 2 Go Electrician Workwear Supplier
These Official Forum Sponsors May Provide Discounts to Regular Forum Members - If you would like to sponsor us then CLICK HERE and post a thread with who you are, and we'll send you some stats etc

Advert

Daily, weekly or monthly email

Thread starter

Joined
Location
Pembrokeshire
Business Name
K H Electrical

Thread Information

Title
Notification Required?
Prefix
N/A
Forum
UK Electrical Forum
Start date
Last reply date
Replies
10

Advert

Thread statistics

Created
KevinH,
Last reply from
Eric12,
Replies
10
Views
1,814

Advert