Gents, in need of your experience/knowledge.

Im working in maintenance at a student accommodation. ( over 900 rooms, over 60 boards )

The buildings need their periodic inspection and testing.

Im trying to be as less disruptive as possible so am just turning the circuits off under test. However, im finding this really uncomfortable, what with the arching and cpcs squeezed behing the line cables. I have asked permission to turn the board off, but this isnt really an option as the rooms all have fridges in and the students are forever studying. My question, can i obtain R1 + R2 by taking my highest Zs reading, calling the Elec board up and getting a true reading of Ze, and making a calculation. I just cant see how this would be good enough to put on a cert as the board will only give me a Ze from the intake room for starters. Plus the fact Zs will have parallel paths. Before i get abused, yes i have my 2395, although my experience in testing is limited. ( Thrown in at the deepend )

Thanks guys.

Tom
 
It shouldn't do any harm to the fridges to knock the power off for a couple of hours per board. Food stays cold for hours. Daz
 
The students have been warned, you have permission just switch off and do the necessary, as above also if the fridge is shut its a good 4hrs before temp' rise is a worry ..... think you're trying to be too accomodating here ..not a bad trait but with that number of flats you need to establish a good routine and repeat without all this trying to avoid disruption ...I see you lose multiple flats if you switch off a board - in this case section the boards and do them in quarters and have a helper so you can race through the testing together.

Do we have 15 flats per Sub main then?
 
Last edited by a moderator:
  • Like
Reactions: 2 people
So in each board i have 13 power and 13 lighting circuits. Each circuit feeds 2 rooms. So 26 rooms per sub board. Yeah ill have to just gain permissio to turn the board off, i was hoping theyd be an easier way by calculating but thats being lazy. thanks guys for confirming.
 
The only way you will get an accurate Ze is by measurement, which means isolating the whole installation and isolating the earth. However to backwards calculate you would need Zdb which is the Zs of the submain feeding the board.
What is acceptable for radials is to use a wander lead to test R2 for each circuit, although this wouldn't prove polarity unlike the R1+R2 test
 
  • Like
Reactions: 1 person
Just turn it off, tell them the more they moan the longer it will be off. Power of being a sparky. Fridge is fine for 24hrs so long as you dont open them and most people use laptops nowadays. Always put your own saftey first, if your not happy working on a live board, dont. You only have 1 life but you can always get another job :cool:
 
  • Like
Reactions: 2 people
I've seen the outcome of someone being pressured into working on a live board. Outcome being a hole burnt through his hand.

It's fine to use Zs as your R1+R2 reading as per GN3.

Jim
 
For an EICR it is not generally necessary to test R1+R2,that test is really intended for initial verification on a circuit prior to energising.What an EICR is really concerned with is adequacy of earthing and disconnection times. In order to minimise disruption carry out Zs tests on each circuit,as long as they are good and as expected then it is reasonable to assume satisfactory R1+R2. It helps if the original EIC is available as then Zs test results can be compared and if they are ballpark close then again,it is reasonable to assume satisfactory R1+R2. You will still have to isolate the entire DB in order to carry out IR tests. This is best done once all circuits have been inspected and Zs tested,and then a global test can be carried out in a very short time with minimum disruption.
There will be those who will throw their toys out of the pram at a practical approach to EICR's. But in my experience they are keyboard warriors who have never actually carried out an EICR in a real world situation where major disruption is not viable and cost and time IS a consideration.
 
  • Like
Reactions: 9 people
you still have to think about the computers tho (hope no wannabe law students there) :D
 
the silly buggers willl have to stop playing internet games for a short while when the wi-fi goes down.
 
  • Like
Reactions: 1 person
the silly buggers willl have to stop playing internet games for a short while when the wi-fi goes down.
the smart ones will use there phones anyway.the rest well can read a book lol
 
yeah, coz daddy's a lawyer/accountant/doctor and has provided them with a contract smartphone, tax deductible.
 
yeah, coz daddy's a lawyer/accountant/doctor and has provided them with a contract smartphone, tax deductible.

but doesn't stop them compiling to daddy and getting daddy to write a formal letter to ask why the wifi/power went off :D
 
sod 'em anyway. students are animals.
 
Please make sure you do a "soft test" 250V IR L&N to earth. With the amount of laptops, mobile phones, Ipods, Sky hubs etc in these places you could open up a world of financial problems for a simple mistake on this scale.

That reminds me. I've got 4 blocks of student accommodation to do an EICR upon in the next few months. Each block is 9-14 stories tall! Never seen inside, no idea what is going to pop up? We just have to be methodical, planned, informed and inform others (tenants,24/7 alarm company, fire brigade if need be etc, cctv security room, any other staff working in the building/s).

God luck with it and ask any questions you have, sure we will all give you support on a job this size. It is not an every day thing.
 
  • Like
Reactions: 2 people

Similar threads

OFFICIAL SPONSORS

Electrical Goods - Electrical Tools - Brand Names Electrician Courses Green Electrical Goods PCB Way Electric Underfloor Heating Electrician Courses Heating 2 Go Electrician Workwear Supplier
These Official Forum Sponsors May Provide Discounts to Regular Forum Members - If you would like to sponsor us then CLICK HERE and post a thread with who you are, and we'll send you some stats etc

Advert

Daily, weekly or monthly email

Thread Information

Title
Heeeellpp!!!!
Prefix
Forum
UK Electrical Forum
Start date
Last reply date
Replies
19

Thread Tags

Advert

Thread statistics

Created
tuckerkop81,
Last reply from
Paul.M,
Replies
19
Views
2,053

Advert