Hi Guys,
I have been asked to run a supply to a portakabin temporary office, this is something that I have never done before and just wanted to confirm that my feelings are correct.
Am I correct in thinking that the temporary building should have a TT supply as there is extraneous metal parts or is it in fact ok to run a TN supply across to it, I am aware that the extraneous requires bonding btw.
Thanks in advance but it is the word temporary which makes me think TT
The cost implications are similar so tbh I would rather do it the best possible way.
I have been asked to run a supply to a portakabin temporary office, this is something that I have never done before and just wanted to confirm that my feelings are correct.
Am I correct in thinking that the temporary building should have a TT supply as there is extraneous metal parts or is it in fact ok to run a TN supply across to it, I am aware that the extraneous requires bonding btw.
Thanks in advance but it is the word temporary which makes me think TT
The cost implications are similar so tbh I would rather do it the best possible way.