chrissolar

Hi Guys,

We installed a 3.68kw Solar PV on a property in October 2012, sent off the DNO application G83 Commissioning form and all went through fine with the DNO.

Yesterday had a call from their next door neighbour which is on the same street and they want to go ahead and proceed with a 3.68kw system, now do I have to submit a single G83 commissioning form or do I have to do a prenotification G83/stage 2, Im sure i read something about a 28 day ruling but cant find anything on the DNO site.

Any advice id be really grateful, cheers in advance

Chris
 
My understanding is that you do not have to pre notify because of the 28day rule. There used to be a sticky on here with a link to the document on the thread buts its been moved. don't have the documents to hand to send the link. call the DNO to point you in the direction of document.
 

Similar threads

OFFICIAL SPONSORS

Electrical Goods - Electrical Tools - Brand Names Electrician Courses Green Electrical Goods PCB Way Electric Underfloor Heating Electrician Courses Heating 2 Go Electrician Workwear Supplier
These Official Forum Sponsors May Provide Discounts to Regular Forum Members - If you would like to sponsor us then CLICK HERE and post a thread with who you are, and we'll send you some stats etc

Advert

Daily, weekly or monthly email

Thread Information

Title
G83 - New install in same street
Prefix
N/A
Forum
Solar PV Forum | Solar Panels Forum
Start date
Last reply date
Replies
1

Thread Tags

Advert

Thread statistics

Created
chrissolar,
Last reply from
SolarRoofSols,
Replies
1
Views
1,011

Advert