R
rattlehead85
Looking for some thoughts and opinions on this situation.
Looked at a burn out gutted old post office with an above flat needing to be fully rewired with extensive building repairs. The ground floor will be reused as a general office when it reopens.
The D.L.O. head is situated in the post office and is designated to serve both properties. This is a new TN-S 100A single fused head replaced last week. Now i will need to replace the mains to the flat above and also run a supply to a new board in the ground floor shop.
I have suggested running 25mm tails from the head to a henley block and from here splitting into (2x) 60A switched fuses next to the cut-out and labelling both. Would placing them both next to the cut-out be acceptable or would positioning the switch fuse for the upstairs flat be required upstairs next to the meter? If so running 25mm swa through an adaptable box to terminate before sleeving and connecting directly to the henley downstairs be ok?
TBH i cant understand why the D.L.O haven't provided a twin fused cut-out seeing as the supply cable appears to be plenty big enough. They were told the head would need to serve both premises and they said that is what i have to work with!
Looked at a burn out gutted old post office with an above flat needing to be fully rewired with extensive building repairs. The ground floor will be reused as a general office when it reopens.
The D.L.O. head is situated in the post office and is designated to serve both properties. This is a new TN-S 100A single fused head replaced last week. Now i will need to replace the mains to the flat above and also run a supply to a new board in the ground floor shop.
I have suggested running 25mm tails from the head to a henley block and from here splitting into (2x) 60A switched fuses next to the cut-out and labelling both. Would placing them both next to the cut-out be acceptable or would positioning the switch fuse for the upstairs flat be required upstairs next to the meter? If so running 25mm swa through an adaptable box to terminate before sleeving and connecting directly to the henley downstairs be ok?
TBH i cant understand why the D.L.O haven't provided a twin fused cut-out seeing as the supply cable appears to be plenty big enough. They were told the head would need to serve both premises and they said that is what i have to work with!