Evening guys

am looking into becoming registered with niceic so I can do on the side pjs and sign them off. (All above board)

was going to use my parents house as my niceic assessment.

change the fuse board, (will carry out a eicr before and after)
upgrade tails to 25mm main earth to 16mm and Gas is already bonded with 10mm at P.o.e
However incoming water is plastic- then has a metal valve then goes off again into floor in plastic again. (Currently no bonding)

1st question- where do I stand with water bonding?
Im guessing the best thing would be to bond at the 1st bit of copper after the plastic- but how can I determine where that is as it goes off under the floor (most of ground floor is tiles or lamanate floors)
-obviously need to get this correct for the niceic inspector.

2nd question:

am I correct in thinking as long as the new fuse board, tails/main earth/bonding (depending on aboves situation with water) are correct to bs7671 as amended, can there be c2 and c3 on the eicr issued as my work will only be the fuse board? As long as the c2 or c3 are clearly noted on the eicr.

and 3rd question:
the assessment is 1 larger job (fuse board) and one smaller job like a new radial circuit install. Correct?
can both jobs be at same address (in my case my parents house)

i know both of the mentioned jobs are notifiable works- and I have a electrician who is already niceic registered who will be willing to register them as a third party on my behalf.

look forward to reponse

cheers guys

joe
 
you don't want a eicr. you need to complete a eic for the work you do. that will be for the CU change and as full set of test results for each circuit. therefore no codes. as for thew water. find some copper pipe that's accessible. IR test to MET. if you get > 22k ohms, then it's not extraneous and does not require bonding. it may well give a low ohms reading as it's likely to be bonded to the gas at the boiler.
 
you don't want a eicr. you need to complete a eic for the work you do. that will be for the CU change and as full set of test results for each circuit. therefore no codes. as for thew water. find some copper pipe that's accessible. IR test to MET. if you get > 22k ohms, then it's not extraneous and does not require bonding. it may well give a low ohms reading as it's likely to be bonded to the gas at the boiler.

Lovely and quick!

so the assessor won't walk around and put up any c2's if present and query why there not done?
 
My suggestion would be that if you have to ask these questions you're not yet competent enough to be carrying out such work unsupervised. I would seriously consider getting some more knowledge and experience under your belt before carrying out your own work.

My guess however would be, that you won't take a blind bit of notice of what I've just said and that you'll just plough on regardless feeling secure in the knowledge that if the NICEIC say you're competent, then it 'must' be true.
 
My suggestion would be that if you have to ask these questions you're not yet competent enough to be carrying out such work unsupervised. I would seriously consider getting some more knowledge and experience under your belt before carrying out your own work.

My guess however would be, that you won't take a blind bit of notice of what I've just said and that you'll just plough on regardless feeling secure in the knowledge that if the NICEIC say you're competent, then it 'must' be true.

Now that's good
 
i know both of the mentioned jobs are notifiable works- and I have a electrician who is already niceic registered who will be willing to register them as a third party on my behalf.

So you are kicking off your NICEIC membership by breaking the rules?

Madness
 
Lovely and quick!

so the assessor won't walk around and put up any c2's if present and query why there not done?

he bloody well will, mate, if he's anywhere near competent. if you change a CU, then any dangerous parts of the installation must be rectified.
 

Reply to Bonding to plastic water pipe in the Periodic Inspection Reporting & Certification area at ElectriciansForums.net

Similar Threads

I'm practising EICRs on friendly locations as I'm still in training - technically done my 2391-52 but frankly need loads more practise. I've just...
Replies
11
Views
917
Hi everyone Ive just had an electrical condition report conducted on a mixed-use property, and I am extremely surprised that after the last report...
Replies
11
Views
2K
Hello. Non-electrician here. Failed an EICR yesterday as the electrician graded my consumer unit C2. Why C2 and not C3? He didn't say (and still...
Replies
22
Views
3K
Recently visited a new build to do a very minor job and spotted a few dodgy looking items so Client asked me to do an EICR. Following items I...
Replies
6
Views
971
Hey all :-) Hope its chill that I'm here asking questions, I just inherited this old decrepit place in NSW (Australia) and went to wash my hands...
Replies
2
Views
851

OFFICIAL SPONSORS

Electrical Goods - Electrical Tools - Brand Names Electrician Courses Green Electrical Goods PCB Way Electrical Goods - Electrical Tools - Brand Names Pushfit Wire Connectors Electric Underfloor Heating Electrician Courses
These Official Forum Sponsors May Provide Discounts to Regular Forum Members - If you would like to sponsor us then CLICK HERE and post a thread with who you are, and we'll send you some stats etc

YOUR Unread Posts

This website was designed, optimised and is hosted by untold.media Operating under the name Untold Media since 2001.
Back
Top
AdBlock Detected

We get it, advertisements are annoying!

Sure, ad-blocking software does a great job at blocking ads, but it also blocks useful features of our website. For the best site experience please disable your AdBlocker.

I've Disabled AdBlock