Hi All

I am quoting a customer for a 25kw system on a commercial property.

The property is used as a gym and has very high electricity use.

Initial calculations estimate 95% self generation with the 25kw system.

My question is, will my customer still receive deemed export payments of 50% or, will he be forced to install an export meter?
 
Presume you mean '95% self consumption'.

The mandatory export meter requirement kicks in at 30kW so you should be OK but some FiT suppliers can be sniffy.
 
Thanks, I thought as much.

So I should be ok with it being under 30kw. Can the FIT supplier make the customer install an export meter or would they have to install it themselves at their own cost? (which I would think is unlikely)
 

Similar threads

OFFICIAL SPONSORS

Electrical Goods - Electrical Tools - Brand Names Electrician Courses Green Electrical Goods PCB Way Electric Underfloor Heating Electrician Courses Heating 2 Go Electrician Workwear Supplier
These Official Forum Sponsors May Provide Discounts to Regular Forum Members - If you would like to sponsor us then CLICK HERE and post a thread with who you are, and we'll send you some stats etc

Advert

Daily, weekly or monthly email

Thread Information

Title
Export payments for a 25kw system
Prefix
N/A
Forum
Solar PV Forum | Solar Panels Forum
Start date
Last reply date
Replies
2

Thread Tags

Advert

Thread statistics

Created
SolarTechWales,
Last reply from
SolarTechWales,
Replies
2
Views
941

Advert