Brixnmorta
The title says it all really, he says that he never registers installations with the DNO unless they are over 4kW.
Every forum I have read says that DNO registration is part of the installation process as much as registering with a supply company for the FIT.
Is there a concise statement of the law on this as I understand it is a legal requirement for installations to be registered within 27 days of commissioning. What penalties are there for not doing so and do they apply to me the customer or the installer?
With thanks
Brixnmorta
Every forum I have read says that DNO registration is part of the installation process as much as registering with a supply company for the FIT.
Is there a concise statement of the law on this as I understand it is a legal requirement for installations to be registered within 27 days of commissioning. What penalties are there for not doing so and do they apply to me the customer or the installer?
With thanks
Brixnmorta